HomeFATA Rural Livelihood and Community Infrastructure Project

rsz 1rlcip project sheet

Grant Amount: US$ 8.1 million (additional financing)
Duration: March 28, 2017 - December 31, 2018
Progress towards acheivement of objective: Moderately Satisfactory
Overall Implementation Progress: ModeratelyUnsatisfactory
Disbursement Status: On track
FATA and FR Regions

Implementing Agency

FATA Secretariat

PCNA Pillar

Strategic Objective 1: Build Responsiveness and Effectiveness of the State to restore citizen's trust

Strategic Objective 2: Stimulate employment and livelihood opportunities

Strategic Objective 3: Ensure the delivery of basic services


To improve livelihoods and access to basic service infrastructure in FATA


Rural Communities of FATA


US$ 0.3 million

Achievements as of June 2017

  • A total of 51 new infrastructure schemes planned in Bajaur, Mohmand and South Waziristan agencies.

  • Project Operations Manual, procurement, environmental and social safeguard plans prepared for project operationalization.

  • Worked with the World Bank’s team on CASA-1000 CSP for almost 4 weeks to finalize its Community Support Programme (CSP) Modality, Procurement and Financial Mechanisms as well as its Communication Strategy, and

  • Prepared the revised PC-1 and Terms of Reference for hiring the Internal Audit Firm.